Tensioned Foundations
POST-TENSIONING
INSTITUTE CERTIFICATION

Established
in 1976, the Post-Tensioning Institute is recognized as
the world-wide authority on post-tensioning. PTI is dedicated
to expanding post-tensioning applications through marketing,
education, research, teamwork, and code development while
advancing the quality, safety, efficiency, profitability,
and use of post-tensioning systems. Members of the Institute
include major post-tensioning materials fabricators in the
U.S., Canada, and Mexico, and manufacturers of prestressing
materials in the U.S., Canada, Mexico, Japan and Europe,
and companies supplying materials, services and equipment
used in post-tensioned construction. In addition, PTI has
more than 500 professional engineers, architects, and contractors.
Most
residential foundations in the United States are constructed
with rebar or wire mesh as their reinforcement to minimize
shrinkage cracks and to resist the stresses created by the
weight of the building. An alternative is the use of post-tensioned
strands in lieu of conventional bonded reinforcing. Post-tensioned
foundations have been around since the 1960s and historically
have been used for expansive and compressive soil conditions
that are prevalent in Texas, California, and other parts
of the Southwest. Contractors and engineers have been taught
that concrete is bad in tension and good in compression,
so it is in the best interest of the concrete to be in compression.
The
general philosophy of post-tensioning is to apply a large
enough force to the concrete such that any tensile stresses
are reduced to acceptable levels. Placing the concrete in
a compressed state will minimize the potential for cracking
and improve the integrity of the slab. With their excellent
performance, relative ease of construction, and economy,
post-tensioned residential foundations are becoming a more
standard foundation system for residential construction
regardless of soils classification.

Post-tensioned
foundations are designed using the Post-Tensioning Institute
(PTI) method first published in 1980 and recently updated
with its 3rd edition. Aside from the reinforcement, the
construction of the foundation is the same as a conventional
system. For most single-family residential construction,
the slabs are 4 to 5 inches thick and have tendons at approximately
4 feet on center in each direction. The tendons are placed
in the center of the slab and continue at this elevation
across the foundation. The specific location of the tendons
is relatively arbitrary. Provided the correct number of
tendons are installed and effectively equally spaced, variations
in tendon spacing will not affect the performance of the
foundation. Gaps between adjacent strands of up to 6 feet
are acceptable. The relatively small number of strands allows
for easier inspection, structural observation, and identification
of problems. In addition, the workers have plenty of room
to move during placing of the concrete to avoid stepping
on the strands and pushing them into the dirt. Since their
exact location is flexible, contractors will often place
the tendons to avoid penetrations and other embedded items.
If a conflict does occur, the strands can curve around the
obstruction, provided the bend is in a smooth and gradual
manner. The majority of post-tensioned foundation plans
will show every strand across the slab, a callout for its
length, a color code for identification, and the expected
elongation from a successful stress. In contrast to elevated
construction, the engineered drawings effectively serve
as shop drawings and the post-tensioning materials should
be able to be fabricated and placed directly from the permitted
plans.
The
tendons can be 15 to 200 feet long and will be delivered
to the site as one continuous piece. They are shipped in
rope-like coils to the jobsite and take up a relatively
small amount of room in comparison with a series of 60-foot-long
pieces of rebar. The contractors must take care to place
the tendons essentially straight with no localized "kinks"
vertically or horizontally along their length. During the
stressing operation, the kinks in the tendons will try to
straighten which can cause localized cracking if the discontinuity
is severe.
Except
in cases of extremely large expansive soils, the tendons
do not extend into the footings. The numbers of tendons
are calculated to provide a minimum of 50 pounds per square
inch of compression over the entire foundation and must
account for frictional losses of the concrete grinding against
the subgrade. When a post-tensioned foundation is used on
stable soils, maintaining the 50-psi minimum is the only
additional calculation from a conventional reinforced foundation.

The
PTI design method incorporates slabs with exterior and interior
footings (ribs) that extend from one end of the foundation
to the other. The interior footings occur in both directions
and add strength and stiffness to resist any applied loading.
Depending on the weight of the building and soil parameters,
the footings are typically 18 to 24 inches deep and 12 inches
wide. The PTI method requires minimal rebar, if any, however
most engineers include one or two #4 bars in the bottom
of the footings. Most geotechnical reports require a minimum
embedment of 12 to 18 inches below the lowest adjacent grade.
This depth activates the appropriate bearing pressure and
provides a partial water stop to minimize moisture intrusion
under the foundation. The footings are typically located
under bearing or shear walls and are spaced approximately
12 feet on center in each direction. If longer spanning
joints or trusses are used, the interior footings may not
align with any structural or architectural element.
If
a ribbed foundation is designed, the system can be converted
into a uniform thickness mat. The conversion requires that
the section properties of the mat be equal or greater than
the rib design. Instead of having a 5-inch-thick slab with
several 24-inch-deep footings, a 10-inch-thick solid slab
can be used. The uniform thickness slabs will have more
concrete and therefore more tendons but substantially less
trenching. In most cases, the only trenching required will
be on the exterior of the foundation. I recommend a minimum
uniform thickness of 8 inches but with larger buildings
with severe soil conditions, slabs in a 14- to 18-inch range
have been used in residential construction. Both methods
are acceptable and are typically chosen by the owner/contractor
based on their preference of placing more concrete or performing
more trenching. From an engineering standpoint, the primary
difference is that the mat foundation will require additional
detailing for anchor and hold-down bolts. Standard off-the-shelf
hardware will typically require more embedment than the
thickness of the uniform mat. Washers connected with a nut
to the bottom of the longer bolts in conjunction with additional
rebar are common in uniform mat construction.
In
addition to resisting soil movement, post-tensioned slabs
have excellent load capacity and effectively remove the
need for isolated pad footings from the foundation. A good
rule of thumb is for every inch of slab thickness, a 1000-pound
post load can be supported. For example, a 5-inch slab can
support a 5000-pound post load without additional concrete
or rebar. An experienced post-tensioning engineer will probably
be able to generate larger capacities depending on concrete
strength and force applied from the tendons. Typical interior
and exterior footings support a 15,000-to 20,000-pound post
load without additional reinforcement. In addition to resisting
post loads, the typical post-tensioned slab will support
standard bearing wall loads for residential construction
without a deepened section. Both the Uniform Building Code
(UBC) and the International Building Code (IBC) provide
formulas to compute the load capacity of the slab to support
bearing walls. This inherent load resistance has proven
very useful in additions where new post and bearing walls
are often introduced and typically require removing some
portion of the existing concrete and building new footings.
The
typical post-tensioned strands are comprised of seven high
tensile strength steel wires that are coiled together to
create a ½-inch-diameter strand. The wires are high
tensile steel having a yield strength of 270 kips per square
inch (ksi), which is substantially larger than the standard
40- and 60-ksi rebar. In contrast to conventional reinforcing,
the strands have no direct bond to the concrete along their
length. The strands are encased in grease and covered by
an extruded plastic sheathing. The sheathing prevents a
bond between the strand and the concrete, while the grease
allows the strand to slide inside the sheathing. The ability
of the strand to move freely is critical because each tendon
will be stretched by a hydraulic jack after the concrete
has been placed. Each strand will be loaded to 33,000 pounds
at stressing. Unlike rebar that is activated only once the
concrete begins cracking, the force from the strands is
always present in the slab to resist applied loading and
minimize cracking.
The
force in the strands is transferred to the concrete by an
anchor at each end that is embedded into the slab. The anchor
is a ductile iron casting with a plan dimension of 5¼
x2 inches and a tapered hole in the center. Two small wedges
placed around each side of the strand physically clamp the
steel wires to the anchor. The anchor and wedges may appear
small, but this system has been used for decades and is
the same assembly that is used in elevated concrete construction.

The
Post-Tensioning Institute recommends that the tendons be
stressed between 3 to 10 days after the concrete has been
placed and has obtained a minimum compressive strength of
2000 psi. The time between placing and stressing is an issue
because the tendons are "unbonded" to the concrete
and are effectively useless for crack control as the slab
cures and shrinks. Until the tendons are stressed, the slab
is essentially un-reinforced, and, if left in this condition,
noticeable cracking is to be expected.
There
is no difference in the concrete used between post-tensioned
and conventional foundations. I recommend a minimum compressive
strength of 3000 psi to allow the mix to reach 2000 psi
within a few days and the tendons to be stressed within
a week of pouring the slab.

The
jacking system is typically operated by a two-person crew.
One person handles the jack and the other operates the hydraulics.
An experienced crew can stress a single-family home in less
than an hour. Once the jack is attached to the tendon and
is bearing against the anchor, the hydraulics are activated.
When the appropriate gauge pressure is achieved, the jack
will hold the force while the wedges are pushed into the
tapered hole, locking the strand to the anchor and their
force to the foundation. To achieve the 33,000 pounds of
load, each strand is stretched approximately 0.08 inch for
every foot of length. For a 50-foot-long strand, the required
elongation will be 4 inches. After the tendons are stressed,
the deputy inspector will measure the elongation and as
long as they are within 7% of the calculated value, the
tails of the strand can be removed. A rust-resisting spray
is applied to the exposed anchor and tail, and the stressing
pocket is filled with a grout to provide cover to the end
of the assembly.